考虑返工的项目进度缓冲管理框架研究
Research on Buffer Management Framework for Project Schedule Control in Rework Scenarios

DOI: 10.12677/mse.2024.132045, PP. 428-441

Keywords: 返工,关键链项目管理,设计结构矩阵
Rework
, Critical Chain Project Management, Design Structure Matrix

Full-Text   Cite this paper   Add to My Lib

Abstract:

作为项目进度延期的重要原因之一,返工一直以来都是项目管理中的难点。尽管关键链项目管理方法为应对项目进度风险提供了有力的工具,但它假设活动的持续时间是互相独立的,在返工情境下并不适用。此外,活动因潜在返工而拥有的特征也未在进度管理中被利用。因此,本文试图提出一个返工情境下的缓冲管理框架,以填补这块空白。具体来说,本文引入设计结构矩阵来描述活动之间的依赖关系,以更精确地确定缓冲大小;此外,本文利用活动因返工而拥有的敏感性指标对缓冲进行分配,以将管理者有限的注意力集中在最关键的活动上。最终,模拟结果表明,本文提出的缓冲管理框架可以提供更可靠的项目工期估计并获得更高的项目按时完工率。
As a major cause of the prolonged project process, rework has long been a challenge in project management. Although critical chain project management provides a powerful tool for dealing with schedule risks, it assumes activities’ durations are independent of each other, which is inappropriate in rework situations. Besides, activities’ features that arising from potential rework are not utilized in schedule management. Hence, this paper tries to propose a buffer management framework in rework scenarios to fill the gap. Specifically, a design structure matrix is introduced to depict activities’ dependencies, thus the buffer size can be determined more precisely. Meanwhile, a sensitivity indicator related to rework is applied to allocate buffer, thus managers’ attention can be focused on the most critical activities. Finally, the simulation result demonstrates that the proposed framework in this paper can provide a more reliable estimate of the project duration and obtain a higher on-time completion rate.

References

[1]  Goldratt, E.M. (1997) Critical Chain. The North River Press, New York.
[2]  Forcada, N., Gangolells, M., Casals, M. and Macarulla, M. (2017) Factors Affecting Rework Costs in Construction. Journal of Construction Engineering and Management, 143, Article ID: 04017032.
https://doi.org/10.1061/(ASCE)CO.1943-7862.0001324
[3]  肖宇. 基于项目返工的关键设计结构矩阵进度优化研究[D]: [博士学位论文]. 上海: 同济大学, 2016.
[4]  Raz, T., Barnes, R. and Dvir, D. (2003) A Critical Look at Critical Chain Project Management. Project Management Journal, 34, 24-32.
https://doi.org/10.1177/875697280303400404
[5]  张静文, 李若楠. 关键链项目调度方法研究评述综述与评论[J]. 控制与决策, 2013, 28(9): 1281-1287.
[6]  Herroelen, W. and Leus, R. (2001) On the Merits and Pitfalls of Critical Chain Scheduling. Journal of Operations Management, 19, 559-577.
https://doi.org/10.1016/S0272-6963(01)00054-7
[7]  Newbold, R.C. (1998) Project Management in the Fast Lane: Applying the Theory of Constraints. The St. Lucie Press, Boca Raton.
[8]  Herroelen, W. and Leus, R. (2005) Project Scheduling under Uncertainty: Survey and Research Potentials. European Journal of Operational Research, 165, 289-306.
https://doi.org/10.1016/j.ejor.2004.04.002
[9]  Tukel, O.I., Rom, W.O. and Eksioglu, S.D. (2006) An Investigation of Buffer Sizing Techniques in Critical Chain Scheduling. European Journal of Operational Research, 172, 401-416.
https://doi.org/10.1016/j.ejor.2004.10.019
[10]  Icmeli, O. and Erenguc, S.S. (1996) A Branch and Bound Procedure for the Resource Constrained Project Scheduling Problem with Discounted Cash Flows. Management Science, 42, 1395-1408.
https://doi.org/10.1287/mnsc.42.10.1395
[11]  Zhao, Z.Y., You, W.Y. and Zuo, J. (2010) Application of Innovative Critical Chain Method for Project Planning and Control under Resource Constraints and Uncertainty. Journal of Construction Engineering and Management, 136, 1056-1060.
https://doi.org/10.1061/(ASCE)CO.1943-7862.0000209
[12]  Leach, L.P. (2006) Critical Chain Project Management. 2nd Edition, Artech House, London.
[13]  别黎, 崔南方. 关键链动态缓冲监控方法研究[J]. 中国管理科学, 2010, 18(6): 97-103.
[14]  Hu, X.J., Cui, N.F., Demeulemeester, E. and Bie, L. (2016) Incorporation of Activity Sensitivity Measures into Buffer Management to Manage Project Schedule Risk. European Journal of Operational Research, 249, 717-727.
https://doi.org/10.1016/j.ejor.2015.08.066
[15]  Zhang, J.G., Jia, S.K. and Diaz, E. (2018) Dynamic Monitoring and Control of a Critical Chain Project Based on Phase Buffer Allocation. Journal of the Operational Research Society, 69, 1966-1977.
https://doi.org/10.1080/01605682.2017.1415641
[16]  Hu, X.J., Cui, N.F. and Demeulemeester, E. (2015) Effective Expediting to Improve Project Due Date and Cost Performance through Buffer Management. International Journal of Production Research, 53, 1460-1471.
https://doi.org/10.1080/00207543.2014.948972
[17]  Steward, D.V. (1981) The Design Structure System: A Method for Managing the Design of Complex Systems. IEEE Transactions on Engineering Management, 28, 71-74.
https://doi.org/10.1109/TEM.1981.6448589
[18]  Steward, D.V. (1981) Systems Analysis and Management: Structure, Strategy, and Design. Petrocelli Books, Princeton.
[19]  Eppinger, S.D. and Browning, T.R. (2012) Design Structure Matrix Methods and Applications. MIT Press, Cambridge.
https://doi.org/10.7551/mitpress/8896.001.0001
[20]  Browning, T.R. (2016) Design Structure Matrix Extensions and Innovations: A Survey and New Opportunities. IEEE Transactions on Engineering Management, 63, 27-52.
https://doi.org/10.1109/TEM.2015.2491283
[21]  Smith, R.P. and Eppinger, S.D. (1997) A Predictive Model of Sequential Iteration in Engineering Design. Management Science, 43, 1104-1120.
https://doi.org/10.1287/mnsc.43.8.1104
[22]  Browning, T.R. and Eppinger, S.D. (2002) Modeling Impacts of Process Architecture on Cost and Schedule Risk in Product Development. IEEE Transactions on Engineering Management, 49, 428-442.
https://doi.org/10.1109/TEM.2002.806709
[23]  Cho, S.H. and Eppinger, S.D. (2005) A Simulation-Based Process Model for Managing Complex Design Projects. IEEE Transactions on Engineering Management, 52, 316-328.
https://doi.org/10.1109/TEM.2005.850722
[24]  Wang, W.C., Liu, J.J. and Liao, T.S. (2006) Modeling of Design Iterations through Simulation. Automation in Construction, 15, 589-603.
https://doi.org/10.1016/j.autcon.2005.07.010
[25]  Lévárdy, V. and Browning, T.R. (2009) An Adaptive Process Model to Support Product Development Project Management. IEEE Transactions on Engineering Management, 56, 600-620.
https://doi.org/10.1109/TEM.2009.2033144
[26]  Steyn, H. (2002) Project Management Applications of the Theory of Constraints beyond Critical Chain Scheduling. International Journal of Project Management, 20, 75-80.
https://doi.org/10.1016/S0263-7863(00)00054-5
[27]  Martens, A. and Vanhoucke, M. (2017) A Buffer Control Method for Top-Down Project Control. European Journal of Operational Research, 262, 274-286.
https://doi.org/10.1016/j.ejor.2017.03.034
[28]  Baldwin, A., Austin, S., Hassan, T. and Thorpe, A. (1998) Planning Building Design by Simulating Information Flow. Automation in Construction, 8, 149-163.
https://doi.org/10.1016/S0926-5805(98)00059-4
[29]  Lin, J., Chai, K.H., Wong, Y.S. and Brombacher, A.C. (2008) A Dynamic Model for Managing Overlapped Iterative Product Development. European Journal of Operational Research, 185, 378-392.
https://doi.org/10.1016/j.ejor.2006.12.022
[30]  Eppinger, S.D., Whitney, D.E., Smith, R.P. and Gebala, D.A. (1994) A Model-Based Method for Organizing Tasks in Product Development. Research in Engineering Design, 6, 1-13.
https://doi.org/10.1007/BF01588087
[31]  Zhang, J.G., Song X.W. and Diaz, E. (2016) Project Buffer Sizing of a Critical Chain Based on Comprehensive Resource Tightness. European Journal of Operational Research, 248, 174-182.
https://doi.org/10.1016/j.ejor.2015.07.009
[32]  郝可可. 关键设计结构矩阵缓冲区设置和计划生成算法研究[D]: [博士学位论文]. 上海: 同济大学, 2019.
[33]  Meier, C., Yassine, A.A. and Browning, T.R. (2007) Design Process Sequencing with Competent Genetic Algorithms. Journal of Mechanical Design, 129, 566-585.
https://doi.org/10.1115/1.2717224
[34]  Brindle, A. (1981) Genetic Algorithms for Function Optimization. Ph.D. Thesis, University of Alberta, Edmonton.
[35]  Murata T. and Ishibuchi H. (1994) Performance Evaluation of Genetic Algorithms for Flow Shop Scheduling Problems. Proceedings of the First IEEE Conference on Genetic Algorithms and Their Applications, Orlando, 27-29 June 1994, 812-817.
[36]  Zhang, J.G., Song, X.W., Chen, H.Y. and Shi, R.X. (2015) Optimisation of Critical Chain Sequencing Based on Activities’ Information Flow Interactions. International Journal of Production Research, 53, 6231-6241.
https://doi.org/10.1080/00207543.2015.1043157
[37]  Ma, G.F., Jiang, S., Zhu, T.C. and Jia, J.Y. (2019) A Novel Method of Developing Construction Projects Schedule under Rework Scenarios. Sustainability, 11, Article 5710.
https://doi.org/10.3390/su11205710
[38]  Dehghan, R. and Ruwnapura, J.Y. (2014) Model of Trade-Off between Overlapping and Rework of Design Activities. Journal of Construction Engineering and Management, 140, Article ID: 04013043.
https://doi.org/10.1061/(ASCE)CO.1943-7862.0000786
[39]  朱天成. 基于不确定返工情形的项目进度关键设计结构矩阵(CCDSM)研究[D]: [博士学位论文]. 上海: 同济大学, 2017.
[40]  Martens, A. and Vanhoucke, M. (2019) The Impact of Applying Effort to Reduce Activity Variability on the Project Time and Cost Performance. European Journal of Operational Research, 277, 442-453.
https://doi.org/10.1016/j.ejor.2019.03.020
[41]  Vanhoucke, M. (2011) On the Dynamic Use of Project Performance and Schedule Risk Information during Project Tracking. Omega, 39, 416-426.
https://doi.org/10.1016/j.omega.2010.09.006
[42]  Xiao, L., Bie, L. and Bai, X. (2021) Controlling the Schedule Risk in Green Building Projects: Buffer Management Framework with Activity Dependence. Journal of Cleaner Production, 278, Article ID: 123852.
https://doi.org/10.1016/j.jclepro.2020.123852
[43]  Demeulemeester, E. and Herroelen, W. (1992) A Branch-And-Bound Procedure for the Multiple Resource-Constrained Project Scheduling Problem. Management Science, 38, 1803-1818.
https://doi.org/10.1287/mnsc.38.12.1803
[44]  Ma, G.F., Hao, K.K., Xiao, Y. and Zhu, T.C. (2019) Critical Chain Design Structure Matrix Method for Construction Project Scheduling under Rework Scenarios. Mathematical Problems in Engineering, 2019, Article ID: 1595628.
https://doi.org/10.1155/2019/1595628
[45]  Ma, G.F., Wu, M., Hao, K.K. and Shang, S.S. (2021) A DSM-Based CCPM-MPL Representation Method for Project Scheduling under Rework Scenarios. Advances in Civil Engineering, 2021, Article ID: 887830.
https://doi.org/10.1155/2021/8878308
[46]  Eppinger, S.D., Bonelli, S. and Gonzalez, A.M. (2013) Managing Iterations in the Modular Real Estate Development Process. In: Scheurmann, E., et al., Eds., Reducing Risk in Innovation, Hanser, Melbourne, 37-44.
https://doi.org/10.3139/9783446437937.005
[47]  Vanhoucke, M. (2010) Using Activity Sensitivity and Network Topology Information to Monitor Project Time Performance. Omega, 38, 359-370.
https://doi.org/10.1016/j.omega.2009.10.001

Full-Text

comments powered by Disqus

Contact Us

service@oalib.com

QQ:3279437679

WhatsApp +8615387084133

WeChat 1538708413