全部 标题 作者
关键词 摘要

OALib Journal期刊
ISSN: 2333-9721
费用:99美元

查看量下载量

相关文章

更多...

Magnitude of Construction Cost and Schedule Overruns in Public Work Projects

DOI: 10.1155/2013/935978

Full-Text   Cite this paper   Add to My Lib

Abstract:

This study analyzed 363 Clark County Department of Public Works (CCDPW) projects to determine construction cost and schedule overruns in various types and sizes of the projects. The sample projects were constructed from 1991 to 2008, with a total construction cost of $1.85 billion, equivalent to 2012 cost. A one-factor ANOVA test was conducted to determine whether construction cost and schedule overruns significantly varied based on types and sizes of the projects. The study showed that large, long-duration projects had significantly higher cost and schedule overruns than smaller, short-duration projects. 1. Introduction Consistent cost and time overruns of public works projects are not the best use of taxpayer money. In the current economic downturn where tax revenues are lagging, they are particularly detrimental. In the public sector, money spent on project change orders and increased construction time reduces the number and size of the projects that can be completed during any given fiscal year. Various reasons for construction cost and schedule overruns in any project include design error, inadequate scope, weather, project changes, and underestimating the time needed to complete the project. Items omitted from the engineer’s estimate of the projects due to design errors or inadequate scope frequently result in change orders, which increase cost as well as the time of delivery. Underestimating the construction time is detrimental because another important project may be delayed from going to bid until the current project is completed. Many public projects are extensions of a previous project, and inaccuracies in estimating project cost and construction time can result in improper sequencing of related projects or phasing within projects, thus delaying much needed improvements. Decisions on which projects are to put out for bids are based both on the need for improvement in a current facility or construction of a new facility, which is certainly the most important consideration, and on the engineer’s estimated cost and construction time. Underestimating a project’s cost and time is not in the public’s best interest, particularly in an urban area with a rate of growth such as the one recently experienced in Clark County, Nevada. Therefore, this study determined the magnitude of construction cost and schedule overruns in public projects of Clark County, Nevada, so that necessary actions can be taken to control these overruns in future projects. Further, the study investigated whether the magnitude of construction cost and schedule overruns varies

References

[1]  C. T. Jahren and A. M. Ashe, “Predictors of cost-overrun rates,” Journal of Construction Engineering and Management, vol. 116, no. 3, pp. 548–552, 1990.
[2]  J. Odeck, “Cost overruns in road construction—what are their sizesand determinants?” Transport Policy, vol. 11, no. 1, pp. 43–53, 2004.
[3]  D. A. Randolph, K. Rajendra, and J. J. Campfield, “Using risk management techniques to control contract costs,” Journal of Management in Engineering, vol. 3, no. 4, pp. 314–324, 1987.
[4]  M. Roth, An empirical analysis of United States Navy design/build contracts [M.S. thesis], University of Texas, Austin, Tex, USA, 1995.
[5]  M. Konchar and V. Sanvido, “Comparison of U.S. project delivery systems,” Journal of Construction Engineering and Management, vol. 124, no. 6, pp. 435–444, 1998.
[6]  S. M. Vidalis and F. T. Najafi, “Cost and time overruns in highway construction,” in Proceedings of the 4th Transportation Specification. Conference of the Canadian Society for Civil Engineering, pp. 2799–2808, Montreal, Quebec, Canada, June 2002.
[7]  J.-K. Lee, “Cost overrun and cause in Korean social overhead capital projects: roads, rails, airports, and ports,” Journal of Urban Planning and Development, vol. 134, no. 2, pp. 59–62, 2008.
[8]  P. P. Shrestha, G. C. Migliaccio, J. T. O'Connor, and G. E. Gibson Jr., “Benchmarking of large design-build highway projects one-to-one comparison and comparison with design-bid-build projects,” Transportation Research Record, no. 1994, pp. 17–25, 2007.
[9]  D. R. Hale, P. P. Shrestha, G. E. Gibson Jr., and G. C. Migliaccio, “Empirical comparison of design/build and design/bid/build project delivery methods,” Journal of Construction Engineering and Management, vol. 135, no. 7, pp. 579–587, 2009.
[10]  T. R. Warne, Design Build Contracting for Highway Projects: A Performance Assessment, Tom Warne & Associates, LLC, 2005.
[11]  L. Burns, Analyzing cost and schedule growth in Public Works Projects [M.S. thesis], University of Nevada, Las Vegas, Nev, USA, 2008.
[12]  Engineering News-Record (ENR), General Contracting Cost Book, vol. 1, McGraw-Hill Construction, New York, NY, USA, 2012.
[13]  E. Weinstein, “Wolfram math world, the web’s most extensive mathematics resource,” 2012, http://mathworld.wolfram.com/ANOVA.html.
[14]  T. Hill and P. Lewicki, Statistics—Methods and Applications, Stat Soft, Inc, Tulsa, Okla, USA, 2006.

Full-Text

Contact Us

service@oalib.com

QQ:3279437679

WhatsApp +8615387084133